Vidin-Calafat Bridge ready in 2012 or 2013
FCC said that “if the weather is nice”, the bridge will be fully completed by the end of 2012 but “if the temperatures during the winter months do not allow this, the final layer of asphalt and hydroisolation will be left for 2013″.
Currently, Vidin-Calafat Bridge is 81% completed, FCC reported. The adjacent infrastructure of the Vidin-Calafat bridge has been completed more than 90% in the Bulgarian side and 95% in the Romanian side.
The builders have already launched into operation some of the road junction at the bridge, and have completed the international passenger and freight railway terminals in Vidin.